A copy of every exemption request needs to be transmitted to the European Commission and to ACER on receipt.
Within two months, ACER can provide an opinion to the regulatory authorities involved.
If a decision is taken, this must be notified by the NRAs to the European Commission, together with all relevant information.
The decision shall be notified, without delay by the concerned regulatory authorities (or by ACER where the decision is taken by ACER), to the Commission, together with all the relevant information with respect to the decision.
The Commission may request to amend or withdraw the decision to grant an exemption. The exemption expires if the construction of the interconnector has not started within two years yet or the interconnector has not become operational within five years. The exemption may be extended if the delay is due to major obstacles beyond the control of the project promoter.